Industry · Substations

Substation bay commissioning, done right the first time

SUDHARSAN supplies utilities and EPC contractors with the portable test systems they need to commission a substation bay from end to end: CTs, protection relays, breakers, busbar schemes and cables. Our kits have commissioned bays for Power Grid, L&T, ABB and Alstom in India, Ethiopia and Saudi Arabia.

  • Busbar stability to 4000 A
  • Cable hi-pot to 100 kV
  • Relay timing
What we solve

Outcomes for every role on the job

Utility engineer

Bays commissioned right the first time.

EPC contractor

Faster handover and fewer site re-tests.

Testing team

A portable kit for every bay test.

Grid operator

Fewer false trips and blackouts.

Test-point explorer

Where we test in your substation

Pick a test to see where it is done and which SUDHARSAN kit proves it.

SUDHARSAN SI/LTR-20 loading transformer used for ct ratio and polarity
Test point 1 · CT ratio and polarity

SI/LTR-20

Loading transformer

Where
Every line, transformer and bus-coupler bay
Rating
Up to 4000 A
View the SI/LTR-20 →
View all test points as a table
TestWhere in the substationSUDHARSAN kit
CT ratio and polarityEvery line, transformer and bus-coupler baySI/LTR-20: Up to 4000 A
CT knee-point voltageCores feeding differential and distance relaysSI/KPV: SI/KPV-HV7: 0–10 kV AC
Over-current and earth-fault relaysRelay and control panelsSI/CV-200: 0.01–200 A
Breaker contact resistanceSF6 and vacuum breakers, isolators, bus jointsSI/MVD-100: 100 A DC
Cable insulation withstand11–33 kV cables, terminations, switchgearSI/EHV-70/80: To 100 kV AC / 120 kV DC
Busbar primary injectionBusbar differential and REF schemesSI/PIK 4000 A: Heavy current source to 4000 A
FAQ

Frequently asked questions

Which tests are needed to commission a substation bay?

Typically CT ratio and polarity, CT knee-point, relay secondary injection, breaker contact resistance, primary injection of the protection chain and cable hi-pot. SUDHARSAN makes a kit for each.

How do you prove a busbar differential scheme before energising?

Inject a heavy primary current (up to 4000 A) through the busbar zone and read the secondary current at every relay. The scheme must stay stable for through-faults and operate for in-zone faults.

What is a normal breaker contact resistance?

It depends on the maker's limit. Readings should be within that limit and close to each other: for example, 4.2 mV at 100 A is 42 µΩ. A pole far above its neighbours needs attention.

Trusted in substations by
  • Power Grid Corporation of India
  • TNEB
  • ABB
  • Alstom
  • Larsen & Toubro
  • KEC International (Ethiopia)
  • VA Tech Schneider T&D (Riyadh)

Commissioning a substation?

Send us your bay list and CT ratings, and we will recommend the kit set.

Tell us your application. We’ll engineer the test solution. · Technical: +91 98847 01185 · anirudh@sudharsanelektric.com

WhatsApp +91 96558 62424
Other industries

IEC standards are cited for the test method only. SUDHARSAN kits follow that method; they are not certified to the standard.